NODE Update 2.10.2025

  1. All concrete patches are complete.

  2. The gas service is on.

  3. Rough in electrical inspection was passed Tuesday, Feb. 2nd.  The contractor, R. Yoder, is coordinating with the city to activate the service. Once activated, they will need to have a final inspection done.

  4. The contractor had the fire pit lit Thursday morning, Feb 6, using a generator. The electric for the fire pit since service was not on yet. The fire pit works great!

  5. String lights are hung.